PAC Update 6.25 – Pictures! & Segment Deadlines Extended

Phase 1B is Chugging Along!

If you haven’t been around the PAC lately, a lot has changed in the lobby area. Walls and frames have been painted, lobby graphics added, and flooring has been laid. It’s great to see this new herringbone pattern of carpet carry visitors from the entrance into the building.

Flooring scraps are strewn about a new carpet floor with subtle hints of purple streaks. A herringbone pattern of carpet is being laid in the lobby of the PAC. Fresh blue/green paint hugs the columns in the group fitness sutdio.

Phases 1C & 1D Segments Extended

Due to the intricacies of these segments, the deadlines will be extended a few days to provide some breathing room for work to be completed.

  • Phase 1C
    • Was: July 8-18
    • Updated: July 8-22
  • Phase 1D
    • Was: July 15-26
    • Updated: July 15-29

Main Entance

The main entrance is expected to be back online no later than July 8. The detour signs will be removed when the entrance is back online.