April Updates

The renovation project reached several key milestones this month, with significant progress visible across the facility. Notable highlights from April include:

  • Structural Development: The installation of vertical steel for the new climbing wall is now underway, defining the scale of this future focal point.

  • Infrastructure & Systems: Crews have been focused on essential mechanical rough-ins, ensuring the building’s core systems are properly integrated.

  • Interior Finishing: Drywall installation and surface preparation are moving forward steadily, with a primary focus on the locker room areas as we transition toward the final finishing phases.

We are excited to see these structural and interior elements come together as we continue to enhance these spaces.

A narrow shot shows a long hallway with an outcove on the left and various doorways throughout. A construction picture shows a wide angle view of the future functional fitness area. The field is littered with active construction materials and the background highlights a drywall enclosure for future weight equipment.